Maine

A construction code official of the Department or a third-party agency shall conduct periodic inspections and document
compliance with the Uniform Construction Code at intervals that do not exceed 6 months for the following equipment: 
 
(1) Electric elevator.
(2) Hydraulic elevator.
(3) Escalator.
(4) Belt man-lift.
(5) Lumber elevator.
(6) Moving walk.
(7) Orchestra elevator.
(8) Organ elevator.
(9) Limited use/limited application elevator.
(10) Special purpose personnel elevator. 
(11)  Stage elevator. 
(12)  Power sidewalk elevator. 
(13)  Elevators used for construction. 
(14)  Inclined elevator. 
(15)  Rooftop elevator.

Inspection and testing under ‘‘ASME A.18.1-1999’’ with ‘‘A18.1a-2001’’ addenda are required at the following intervals: 
 
(1) Testing under section 10.3.1 shall be conducted at 5-year intervals. 
(2)  Testing under section 10.3.2 shall be conducted at 5-year intervals. 
(3)  Testing under section 10.3.3 shall be conducted at 5-year intervals.